Project Delivery Manual
Physical Resources Service
OCTOBER 2010

Table of Content

Foreword
Purpose of Manuall
Section 1 - General Framework and Business Processes
Section 2 - Roles and Responsibilities
Section 3- Forms and Resources
Section 4 - Glossary of Terms
Appendix A - Procurement of Consulting / Expert Services

 

Foreword

The University of Ottawa adopted a process to assure itself that major investment decisions are taken within the context of its entire portfolio to maximize its return and to meet its overall strategic requirements. For this reason, its approach emphasizes the long-term planning of requirements and the programming of its projects. The University of Ottawa adopted a process to assure itself that major investment decisions are taken within the context of its entire portfolio to maximize its return and to meet its overall strategic requirements.  For this reason, its approach emphasizes the long-term planning of requirements and the programming of its projects.

The Project Management Institute points out those organizations perform work which generally involves either operations or projects, although the two may overlap… “Projects are often implemented as a means of achieving an organization’s strategic plan… Operations are on-going and repetitive while projects are temporary and unique… A project is a temporary endeavour undertaken to create a unique product or service”.

“Project management is the application of knowledge, tools, and techniques to project activities to meet project requirements. Project management is accomplished through the use of processes….”

This manual generally follows Physical Resources Service’s mission and objectives. It describes the project delivery processes used by the service..

Back to top

Purpose of the Manual

This manual is intended to provide a set of guidelines where projects are carried out by the Physical Resources Service at the University of Ottawa. The manual offers management at all levels a clear understanding of the tasks required at each stage of
delivery, where their intervention is necessary, the value of estimates and their relationship to the budgetary process. These tasks are mostly in chronologic order however some tasks may be perform simultaneously.

The different tasks in the manual are mostly intended for medium size projects, other tasks may be mandatory for a large project will some listed tasks may be overlooked for small projects. The PL and Manager (and other members) should use their judgment and experience to address proper tasks depending on the project size and complexity.

Note: The success of a project delivery manual resides on the fact that it is a basis from which it can be continuously improved. Its improvement will depend upon the contribution of all intervening parties to the delivery process. The Director, Physical Resources has the responsibility to administer the manual and to coordinate all modifications to it. If anyone needs clarification or would like to propose a change to the manual, do not hesitate to address them to your immediate supervisor, he/she will then make the formal proposal to the director for review and approval.

Back to top


Section 1: General Framework and Business Processes

General Framework

The project delivery stage has seven (7) stages as illustrated below:

  • Stage 1 – Project Definition
  • Stage 2 – Planning and Development
  • Stage 3 – Design Management
  • Stage 4 – Bid Procurement
  • Stage 5 – Implementation
  • Stage 6 – In-Service
  • Stage 7 - Project Closeout

During the delivery process, each stage has a corresponding approval element and a budget control element as illustrated below.

project stages approval

At each stage of delivery, a Goal is defined, together with the tasks to be achieved and the deliverables.

Goal

The goal defines the expectations and outcomes for the stage.  In project delivery management, outcomes refer to scope (including quality), time, cost and client satisfaction.

Tasks

  • Activities and responsibilities are defined in operational terms to achieve the goal.

Legend

CT
Client
OM
Operations and Maintenance Group
SP
Strategic Planner
PA
Project accounting Group
PL
Project Leader
red dot
Denotes primary responsibility
PM
Project Manager
2 red dots
Denotes significant supporting responsibility
EQA
Engineer, Quality Assurance
red dot empty
Denotes a requirement to be informed
CXA
Project Commissioning Agent
R
F
Resources
f
Forms

See Section 2: Roles and Responsibilities explain more in depth each term.

Deliverables

  • Deliverables are tangibles that are the result of the stage. It could be a Commissioning Report, a
    sketch, a schedule and estimate, etc.

 

Project Delivery

Stage 1 – Project Definition (Définition de projet)

stage 1

Goal

The goal of Project Definition is to define the requirements giving rise to the project in sufficient details for the approval authority to clearly understand the objectives, the justification, and the potential alternatives to perform a feasibility analysis, and the expected outcomes in terms of scope, time and cost.

Tasks

  Task Description
CT
SP
PL
PM
EQA
CXA
OM
PA
R/F
1.1 Identify requirements giving rise to the project.
2 black dot
  black dot            
1.2 Create a project ID with project number and create a project file    
black dot
       
2 black dot
F
1.3 Carry out a cursory investigation (incl VFA impact)    
black dot
 
2 black dot
     
R
1.4 Define scope and / or basic functional and operational requirements empty black dot
black dot
2 black dot
           
1.5 Assess preliminary schedule    
black dot
 
2 black dot
       
1.6 Estimate costs    
black dot
 
2 black dot
 
2 black dot
   
1.7 Define expected delivery method (1)    
black dot
2 black dot
         
1.8 Submit / discuss the proposal to the client 2 black dot  
black dot
           
1.9 Present the project to the “Bureau de projet (SP & ADs’)” for initial approval  
2 black dot
black dot
           
1.10 Obtain go-no-go decision
empty black dot
 
black dot
empty black dot
2 black dot
 
2 black dot
2 black dot
 

(1) During stage 1, delivery options are examined. The AD, PM may, in consultation with the Director, establish that it would be in the interest of the University to immediately retain consultants for the full development of the project (including the planning and development phase). The PM would then have extended responsibilities that will be negotiated case by case with the PL.

Deliverables

  • Class “D” Estimate – Order of Magnitude
  • Project File

 

 

  • Project Identification Document

 

Stage 2 – Planning and Development

Stage 2

 

Goal

The goal of planning and development is to work with the Client, the Users, the Consultants and inhouse specialists to array alternative solutions to meet the objectives of the project identified in stage 1, to analyze the benefits and costs of the alternatives, to recommend one alternative together with the parameters of scope, time and costs parameters in the form of a Project Brief, which once approved will lead to the next stage, Design Management.
The extent of feasibility analysis will depend on the nature, complexity and size of the project.

Tasks

  Task Description                                   
CT
SP
PL
PM
(1)
EQA
CXA
OM
PA
R/F
2.1 Conduct feasibility study    
black dot
           
2.2 Make a preliminary assessment of project viability: special considerations, financing, community impact, zoning / development approval, environmental impact, building conditions, heritage designation, etc.  
2 black dot
black dot
 
2 black dot
       
2.3 Analyze and determine Planning Delivery Method (See task 1.7)    
black dot
2 black dot
         
2.4 Retain in-house or external expertise as required (see Appendix A – Procurement)    
black dot
empty black dot
     
2 black dot
 
2.5 Meet with the client and user representatives to define program requirements
2 black dot
 
black dot
           
2.6 Determine PRS standards applicable to project    
black dot
 
2 black dot
     
R
2.7 Obtain current master drawings    
black dot
         
R
2.8 Assemble a planning team: client representative, user representative, internal / external PM and professionals, commissioning agent and / or O&M representatives as the case might be
2 black dot
 
black dot
2 black dot
2 black dot
2 black dot
2 black dot
   
2.9 Define basic program and technical, operational requirements of the project. Interface with other UO Services providers  
2 black dot
black dot
 
2 black dot
2 black dot
2 black dot
 
R
2.10 Develop available alternative solutions and cost benefit analysis    
black dot
   
2 black dot
     
2.11 Analyze the commissioning delivery options and costs, and integrate in the Project Brief (as applicable)    
black dot
           
2.12 Conduct a risk, value management analysis. Identify designated substances and other H+S issues
2 black dot
2 black dot
black dot
2 black dot
2 black dot
2 black dot
2 black dot
 
R
2.13 Review the recommended solution with the client and users as required
2 black dot
 
black dot
           
2.14 Define the work plan, schedule, swing requirements    
black dot
           
2.15 Estimate costs (incl cash flow)    
black dot
 
2 black dot
     
F
2.16 Define communication requirements    
black dot
           
2.17 Complete Project Brief and obtain approval
2 black dot
 
black dot
         
F
2.18 Transfer Project Brief    
black dot
2 black dot
     
2 black dot
 

 

Deliverables

  • Technical Reports
  • Feasibility and Alternative Studies
  • Designated Substance Report
  • Programming Report

 

 

  • Project Budget (Class C)
  • Project Schedule
  • Schematic Design

 

Stage 3 – Design Management

stage 3

 

Goal

The goal of design management is to translate the requirements and programming as defined in the Project Brief into a conceptual design solution at a level where it can be implemented with working drawings and specifications. There are normally four essential components of design:

  1. Review Functional and Operational Programming
  2. Schematic Design and feasibility analysis
  3. Design Development
  4. Working Drawings and Specifications

The process used by the Project Manager to retain design consultants may vary given the nature, size and complexity of the project. The Project Manager will authorize resources during the delivery of the project.

Tasks

  Task Description                                   
CT
SP
PL
PM
EQA
CXA
OM
PA
R/F
3.1 Review Project Brief; analyze parameters of scope, time, cost and risks      
black dot
         
3.2 Define / update activities (budgeted items) required delivering scope of project and sequencing the activities using a critical path approach      
black dot
         
3.3 Assemble project team (1) and chair a startup meeting to review parameters and planned delivery of project, discuss and resolve issues arising and ensure subsequent follow up. Establish lines of communication within the project team
2 black dot
 
2 black dot
black dot
2 black dot
2 black dot
empty black dot
   
3.4 Obtain architectural, mechanical and electrical master documents and the University Ottawa Commissioning Guide Specifications      
black dot
 
2 black dot
     
3.5 Conduct consultant procurement (see Appendix A – Procurement)      
black dot
 
2 black dot
   
R/F
3.6 Review schematic design, while applying PRS standards
2 black dot
2 black dot
2 black dot
black dot
2 black dot
2 black dot
     
3.7 Review design development plan, commissioning plan and project parameters (scope, time, risk, room numbering and estimated costs) at 33, 66 and 99 % using the members of the project team, as required
2 black dot
 
2 black dot
black dot
2 black dot
2 black dot
     
3.8 Obtain sign-off of plans
2 black dot
 
empty black dot
black dot
2 black dot
2 black dot
     
3.9 Update project information and review project parameters and submit Class B Estimate      
black dot
     
2 black dot
F
3.10 Monthly reports on project parameters to Leader    
empty black dot
black dot
     
2 black dot
F
3.11 Maintain communications with the client and provide regular project updates to the client
2 black dot
 
2 black dot
black dot
         
3.12 Assess potential deviations and recommend changes with a Brief Modifier as required. Scope changes to be processed by Leader (2)
empty black dot
2 black dot
2 black dot
black dot
       
F
3.13 Obtain Brief Modifier approval to proceed to next stage from Leader
2 black dot
 
black dot
2 black dot
empty black dot
empty black dot
 
2 black dot
 

(1) The Project Team is normally headed by the Project Manager and normally includes the Project Leader Planner/Portfolio, the Client and the User Representatives, the Consultant(s), the other services whose involvement is critical (such as Operations and Maintenance, Protection services, communications, Informatics, etc., the commissioning Agent and other advisory Services).
(2) All major scope changes must be submitted by the Project Leader and approved by the “Bureau de project”.

Deliverables

  • 100 % working drawings and specifications for architectural and engineering components
  • Commissioning Plan at 99%
  • Design Development Plan at 99%
  • Implementation Approval
  • Revised Project Estimate (Class B)
  • Brief Modifier, as applicable
  • Sign-off by the client and the users and other team members, as applicable
  • Monthly Executive Report

 

Stage 4 – Bid Procurement

stage 4

 

Goal

The goal of bid procurement is to acquire a construction / renovation at the best possible price in relation to quality.

 

Tasks

 

  Task Description                                   
CT
SP
PL
PM
EQA
CXA
OM
PA
R/F
4.1 Review requirements of the Project Brief for specific instructions with respect to the procurement strategy and procurement method      
black dot
         
4.2 Assemble working drawings & specifications and commissioning requirements and prepare Bid Documents      
black dot
       
F
4.3 Initiate bid process (invited or public bidding process)      
black dot
         
4.4 Arrange for a job showing to describe project, site, requirements and standards, evaluation method, and respond to any inquiries
empty black dot
 
empty black dot
black dot
empty black dot
empty black dot
     
4.5

Respond to inquiries during the bid period and issue addenda, as required (1)

empty black dot
 
empty black dot
black dot
empty black dot
empty black dot
     
4.6 Receive and evaluate bid proposals for conformity      
black dot
         
4.7 Update project and review project parameters as required (scope, time, risk and estimated class A project cost)and monthly executive report
empty black dot
 
empty black dot
black dot
     
2 black dot
F
4.8 If applicable, issue a Brief Modifier to Leader for approval
2 black dot
2 black dot
2 black dot
black dot
       
F
4.9 If applicable, approve Brief Modifier
2 black dot
   
2 black dot
 
empty black dot
 
2 black dot
 
4.10 Negotiate contract if necessary      
black dot
         
4.11 Issue Letter of Intent. Award contract / work order      
black dot
     
2 black dot
F

 

 

(1) If a change occurs in the mechanical / electrical component of the project, the professional engineer will be consulted.

 

Deliverables

 

  • Bid Documents
  • Post – Bid Addendum (if applicable)
  • Post – Bid Addendum (if applicable)

 

 

Approvals

 

    • Project Brief Modifier, as applicable
    • Letter of Intent
    • Contract / Work Order

 

Stage 5 – Implementation

 

stage 5

Goal

 

Project Implementation

The goal of implementation is to ensure the delivery of the built work as defined in the Project Brief on time and on budget. This stage of project delivery ends with the substantial performance.

5.1 Tasks

  Task Description                                   
CT
SP
PL
PM
EQA
CXA
OM
PA
R/F
5.1.1 Organize and chair a job initiation meeting to provide information and to orient the principal contractor to the facility
2 black dot
 
2 black dot
black dot
2 black dot
2 black dot
2 black dot
   
5.1.2 Issue Work Orders and / or Purchase Orders to other service providers, brief them on scope of work and site requirements      
black dot
     
2 black dot
 
5.1.3 Coordinate all activities by chairing regular project meetings or assign activities to University Service providers (Security, CCS, TLSS, Environment, Health and Safety, etc.)
2 black dot
2 black dot
2 black dot
black dot
 
empty black dot
empty black dot
   
5.1.4

Obtain specific information/documents from the contractor related to: Health and Safety Proof of insurance Construction permits Performance Bond (as required) WSIB Clearance Certificate WHIMIS Material Safety Data Sheet Construction schedules Site clean-up requirements Statutory Declaration

     
black dot
   
empty black dot
2 black dot
 
5.1.5

Review with contractor: Progress payment and holdback Record documents requirements Commissioning procedures (as applicable)

     
black dot
 
2 black dot
 
2 black dot
 
5.1.6 Establish communications protocol between the Project Manager and Contractor public relations, records of meetings, etc.      
black dot
         
5.1.7 Analyze and produce monthly critical path schedule, issue tracking and Project Budget Cost Report and Monthly Executive Report
empty black dot
 
empty black dot
black dot
     
2 black dot
F
5.1.8 Evaluate and anticipate risks considering the likelihood of occurrences, ability to control and dollar value      
black dot
         
5.1.9 Carry out regular reviews of site and issue specific instructions in writing      
black dot
         
5.1.10 Organize and chair regular team meetings to discuss and resolve all project related issues and ensure proper follow-up
2 black dot
   
black dot
2 black dot
2 black dot
     
5.1.11 Coordinate all activities surrounding occupancy (move, permits, security, signage, keying, etc.)
2 black dot
   
black dot
         
5.1.12 Before substantial performance, assemble key members of the project team and, together with the contractor, conduct site review to confirm conformity with the contract documents and identify deficiencies
2 black dot
   
black dot
2 black dot
2 black dot
2 black dot
   
5.1.13 Obtain from the consultants a consolidated list and cost of the deficiencies. Include commissioning observation list      
black dot
2 black dot
2 black dot
     
5.1.14 Obtain sign-off from the client and users and other team members subject to deficiencies being remedied
2 black dot
 
2 black dot
black dot
2 black dot
2 black dot
2 black dot
   
5.1.15 Issue Certificate of Substantial Performance to the contractor together with a request to remedy remaining deficiencies within a timeframe    
empty black dot
black dot
     
empty black dot
 
5.1.16 Obtain from the contractor: Operating Manuals Systems Specifications As built drawings in both electronic and paper format Proof of waste management disposal or recycling      
black dot
 
2 black dot
     
5.1.17 Authorize payment of the contract amount less the value of deficiencies subject to Lien Act      
black dot
     
2 black dot
F
5.1.18 Maintain communications with the client and provide regular project updates to the client
2 black dot
 
2 black dot
black dot
         

 

Goal

Change Management

Change is an essential part of project delivery. A change to the project may have an impact on all project parameters: scope (includes quality), time, cost, risk and client satisfaction. The goal of change management is to control and coordinate all changes resulting from errors and omissions, changes in requirements or site conditions to ensure overall project delivery and client satisfaction.

5.2 Tasks

  Task Description                                   
CT
SP
PL
PM
EQA
CXA
OM
PA
R/F
5.2.1 Review Requests for Change      
black dot
         
5.2.2 Identify reason for change and impacts
2 black dot
 
2 black dot
black dot
         
5.2.3 Issue a Contemplated Change Notice      
black dot
         
5.2.4 if applicable, submit Brief Modifier (1)
2 black dot
 
2 black dot
black dot
 
2 black dot
 
2 black dot
F
5.2.5 Issue a Change Order to the contractor as required      
black dot
     
2 black dot
f

(1) All major scope changes must be submitted by the Project Leader and by the “Bureau de projet”.

Deliverables

  • Soft Cost Work Orders / Purchase Orders
  • Change Orders (if applicable)
  • Deficiency Lists
  • Certificate of Substantial Performance
  • Payment Certificates

 

 

  • Revised Project Budget
  • Monthly Executive Report
  • Brief Modifier (if applicable)
  • Project Team Approval and Sign-Off

 

Stage 6 – In-Service

stage 6

 

Goal

The In-Service is concerned with:

  1. Client Acceptance Contractor’s Final Performance,
  2. Hand-Over to Operations and Maintenance
  3. Commissioning.

Client Acceptance

The goal of in-service is essentially to hand-over the facility to its users and maintainers.

 

6.1 Tasks

 

  Task Description                               
CT
SP
PL
PM
EAQ
CXA
OM
PA
R/F
6.1.1 Assemble the relevant members of the project team, particularly the client and user representative, and carry out a final inspection with the contractor to ensure deficiencies have been corrected
2 black dot
 
empty black dot
black dot
 
2 black dot
     
6.1.2 Arrange for the occupancy of the facility for the client (including move management)
2 black dot
 
empty black dot
black dot
         
6.1.3 Obtain the client’ acceptance and sign-off
2 black dot
 
empty black dot
black dot
         

 

Deliverables

 

  • Deficiency Checklist
  • Deficiency Checklist

 

 

 

 

  • Project Team Approval and Sign-Off
  • Project Team Approval and Sign-Off

 

Contractor’s Final Performance, Hand-Over to Operations and Maintenance

The goal in the section is to obtain all official documentation.

6.2 Tasks

  Task Description                                   
CT
SP
PL
PM
EQA
CXA
OM
PA
R/F
6.2.1 Obtain and submit Closeout documents      
black dot
 
2 black dot
     
6.2.2 Issue a Certificate of Final Performance to the contractor      
black dot
     
2 black dot
 
6.2.3 Apply and obtain Occupancy Permit      
black dot
     
2 black dot
 
6.2.4 Release Holdback      
black dot
     
2 black dot
 
6.2.5 Authorize the final payments      
black dot
     
2 black dot
 
6.2.6 Update Project Estimate and Monthly Executive Report    
empty black dot
black dot
     
2 black dot
F

 

Deliverables

 

  • Certificate of Final Performance
  • Deficiency Checklist
  • Guaranties and Warranties
  • Ontario Hydro Certificate
  • Occupancy Permit
  • Occupancy Permit

 

 

 

    • Plumbing Certificate in Inspection
    • Record Drawing (electronic format)
    • Designated Substance Document
    • Statutory Declaration
    • Revised Project Estimate
    • Monthly Executive Report

Commissioning

 

In this section, the Project Manager must insure that the Project Commissioner executes task 6.3.1 to 6.3.5. 

 

6.3 Tasks

  Task Description                                   
CT
SP
PL
PM
EQA
CXA
OM
PA
R/F
6.3.1 Complete building condition impact information  
2 black dot
 
black dot
         
6.3.1 Verify Closeout documents          
black dot
2 black dot
 
6.3.2 Organize operations training session with client and operations group
2 black dot
   
black dot
 
2 black dot
2 black dot
   
6.3.3 Complete Maximo documentation process          
black dot
2 black dot
   
6.3.4 Review Functional Performance Testing      
2 black dot
 
black dot
     
6.3.5 Submit a Final Commissioning Report      
black dot
 
2 black dot
empty black dot
   

 

Deliverables

 

  • Commissioning Report (Final)
  • Test Records
  • Building Automation Systems Graphic

 

 

 

  • Equipment Data Information (For Maximo)
  • Building Condition Impact Information Sheet (for VFA)

 

 

Stage 7 – Project Closeout

stage 7

 

Goal

The goal of project closeout is to ensure that all the control elements of the project have been completed and that the project’s performance is evaluated in terms of the Client’s satisfaction, the Consultant’s performance and the Contractor’s performance.

The Project Manager must ensure that all the accounts have been cleared and that the documentation has been obtained and complies with the stated standards, including record documents, and to the satisfaction of the Client, and that the project files are documented and archived for future reference.

 

 

Tasks
  Task Description                                   
CT
PP
PL
PM
EQA
CXA
PC
OM
PA
R/F
7.1 Ensure that all the accounts are closed      
black dot
       
2 black dot
 
7.2 Perform Project Evaluation of scope, schedule, cost, client satisfaction and contractor/consultant performance
2 black dot
2 black dot
2 black dot
black dot
2 black dot
2 black dot
2 black dot
2 black dot
2 black dot
F
7.3 Submit Project Closeout Documentation Checklist to Leader for approval    
2 black dot
black dot
           
7.4 Transfer completed project to Leader    
black dot
2 black dot
       
2 black dot
 
7.5 Complete documentation archiving                
black dot
 

Deliverables

  • Final Project Cost Report
  • Project Evaluation
  • Project Closeout Documentation ChecklistBack to top

Section 2: Roles and Responsibilities

 Client (CT) – Refers to an individual in authority at the faculty / service. This person is usually an administrative officer.

Commissioning Authority (CXA) - The CXA is an independent authority (coming from external services or from in-house staff in smaller project), not otherwise associated with the A/E team members or the Contractor, who directs and coordinates the commissioning activities and provides reports to the PM and the University of Ottawa’s Commissioning Manager. The CXA is the University of Ottawa’s representative in the day-to-day activities of construction related to commissioning. For external commissioning agent services, the CXA is normally hired by the University of Ottawa directly.

The primary role of the CXA is to coordinate commissioning work during design, review construction documents, adapt commissioning specifications, develop and coordinate the execution of a testing plan, observe and document systems performance — that they are functioning in accordance with the documented Owner’s Project Requirements and Performance Criteria and in accordance with the Contract Documents. The CXA is not responsible for design concept, design criteria, compliance with codes, design or general construction scheduling, cost estimating, or construction management. The CXA may assist with problem-solving or resolving non-conformance or deficiencies, but ultimately that responsibility resides with the general contractor and the A/E. The CXA will normally work with the PM and GC according to established protocols to schedule the commissioning activities. The GC will integrate all commissioning activities into the master construction schedule.

Project Leader (PL) – The Project Leader represents the interest of the University and Faculty or Service. For engineering-based projects, the Project Leader is the EQA. The Project Leader is responsible to define the project program user and assets requirements, the scope schedule and cost to carryout sufficient feasibility analysis to support a decision by the University or the Faculty to invest in a project. The Project Leader will ensure communication with the client throughout the life of the project.

Project Manager (PM) – The Project Manager (PM) is responsible for the delivery of a approved project based on the parameters defined in the Project Brief, in terms of scope (includes quality), time and cost which is prepared by the Facility Manager / Portfolio. Obviously, if the Project Manager does not feel that the project can be carried out within those parameters, the project should not be accepted.

During the delivery of the project, the Project Manager is to advise the Project Leader of any factors that will impact any of the parameter of scope, time and cost that is part of the project. Any variances from any of these factors will require modification to the terms of the Project Brief before proceeding.

Responsibilities include the selection and management of consultants, fee negotiations, programming, cost estimating, site analysis, preparation of construction documents, document review, budget and schedule, construction administration, in-service and closeout.

The Project Manager is responsible for the management and coordination of the: design development, documentation, construction, and defects liability phases. All stakeholders are advised when such transfer of responsibility occurs.

The Project Leader must ensure that sufficient funds exist in the Project Brief should and external project management firm be utilized.

“It is the responsibility of the Project Manager to ensure that resources, manpower and money are expended at the right time and in the right place.”

Professional Engineer, Quality Ensurance (EQA) - He represent the University in the Owner’s role. For this reason, he is accountable to define the mechanical / electrical component of projects in terms of scope, time and costs.

Operations & Maintenance Group (OM) - The activities related to operations and maintenance are associated with performing on-going routine, preventive, predictive, scheduled, and unscheduled actions with the objective of preventing equipment failure or decline, resulting in increased efficiency, reliability, safety as well as ensuring that functional systems and facilities meet the design intent. These activities and/or services also focus on enhancing the life-cycle and performance of assets, while reducing our capital repair costs, reducing unscheduled shutdowns and extending equipment and facility life.

Project Accounting Group (PA) – The Project Accounting group administers the financial aspect of all capital projects. This includes but not limited to project reporting, tracking of funding, estimates and encumbrances.

Strategic Planner (SP) - The Strategic Planners are responsible for the assessment and planning in three key areas of expertise: space programming, facility condition, mechanical and electrical infrastructures. They evaluate the impacts of all planned and proposed development, they advise on the short, medium and long term requirements in their area of expertise.

black dot Denotes Primary responsibility - Activity performed by the individual.

2 black dot Denotes significant supporting responsibility – Does a supporting action.

empty black dot Denotes a requirement to be informed – For information only.

R/F – Resources and Form available.

Back to top

Section 3: Forms and Resources

All Stages


    Resources
  • Mission and Objectives
  • Procedure 19-2 on Selection Procedure for Consultants and Contractors
  • Policy 113 on Maintenance, Renovations, Structural Modifications, Upgrading and Construction
  • Project Administrative Directives #1471
  • Standing offers for Project Management, Consultants and Contractors Forms
    Forms
  • Brief Modifier
  • Monthly Executive Report
  • Project Estimate
  • Canadian Standard Form of Contract for Architectural Services Document 6
  • Schedule “C”
  • Work Order

Stage 1 - Project Definition

    Resources
  • Building Condition Audits (VFA)
    Forms
  • Project Identification Document

Stage 2 - Planning and Development

    Resources
  • Designated Substance Inventory
  • PRS Standard and Condition Guidelines
  • Master Drawing
  • Strategic Guidelines (under review, see SP for information as needed) Forms
  • Project Brief

Stage 3 - Design Management

    Resources
  • Strategic Guidelines (under review, see SP for information as needed)Forms

Stage 4 - Bid Procurement

    Resources
    Forms
  • Bid Document (Long and Short form)
  • General conditions
  • Standard Construction Document (CCDC-2)

Stage 5 - Implementation

    Resources
    Forms
  • Payment Certificate
  • Substantial Performance Certificate

Stage 6 - In- service

    Resources
    Forms
  • Equipment Data Information (for Maximo) (form not available at this time)
  • Building Condition Impact Information Sheet (for VFA) (form not available at this time)

Stage 7 - Project Closeout

    Resources
    Forms
  • Project Delivery Evaluation
  • Final Project Cost Report
  • Brief Modifier Closeout
  • Project Closeout Documentation Checklist

Back to top

 

Section 4 – Glossary of Terms

 

 

Activity is an element of work performed during the delivery of the project. An activity normally has an expected duration, an expected cost and expected resource requirements. Activities can be divided into tasks. 

AD ADM is an abbreviation for the Assistant Director.

AD PM is an abbreviation for the Assistant Director; Project Management.

AD O&M is an abbreviation for the Assistant Director; Trades and Grounds 

Base Building refers to a constructed building prior to occupant fit-up. It includes floors, bearing walls, enclosing walls, ceilings and building systems consistent with the designed function of the building.

Bid Document (Long and short Form)is an abbreviation for the Assistant Director; Planning and Programming.

Adaptation, Renovation and Modernizationdefines the general conditions of the lump sum contract with the general contractor. The short form is used for a contract $250,000 while the long form is used for public tendering (over $250,000).

Brief Modifier - Document that identifies changes (scope, time or/and cost) to the original project brief. All major scope changes must be submitted and approved by the Strategic Planner at the “Bureau de project”.

 

Brief Modifier Closeout - Document that confirms final project cost to client.

Building Condition Audit (via VFA) is a formal inspection to evaluate (rate) the condition of a building and its conformity to building codes. It also serves to identify activities and/or projects to ensure its maintenance, repair, renewal and replacement.

Canadian Standard Form of Contract for Architectural Services Document 6 (2002) – Contracts between the University and the Architect(s) that is recommended by the Royal Architectural Institute of Canada.

 

Classes of Estimates refer to the value of the estimate given the delivery stage. A Class D Estimate, for example, is an “estimated order of magnitude” given at feasibility analysis for decision-making purposes.

 

 

Class of
Estimate
General Description
Inclusions
Project Delivery
Document(s)
Expected
Variance
Project Delivery
Stage
Class D
  • An estimated order of magnitude, strictly only an indication of final cost.
  • Purely for cost comparison between alternative solutions or competing projects.
  • A statement of requirements.
  • An outline solution.
  • Project Identification Document
  • Within 30% of actual project cost
1
Class C
  • Ballpark estimate used only in preliminary discussion of feasibility with approved option.
  • Sufficient for selecting correct investment decisions.
  • Completion of all work necessary to undertake preliminary design.
  • Knowledge of site conditions adequate to enable identification of site related risks.
  • Project Brief
  • Within 20% of actual project cost
2
Class B
  • An estimate based on completed preliminary design documents.
  • Upon acceptance, theses estimates become the cost plans for project cost control during design.
  • This estimate needs to be revised if project parameters change during stage 3.
  • At least two levels of a documented work breakdown structure, definition of major systems and subsystems, preliminary drawings and outline specifications.
  • Developed by project manager and/or subject matter experts.
  • 100% Preliminary Design Documents

    To

  • 100% Working Documents
  • Within15% of actual project cost
3
Class A
  • An owner’s estimate based on complete contract documents and used as a control check on authorized expenditures after bidding.
  • Some soft costs remain budgeted amounts
  • A detailed quantity takeoff and project of time and costs to deliver the entire project.
  • Pre-tender or
  • Awarded
    Contract
  • Within10% of actual project cost
4
Class A Revised
  • An estimate using actual encumbrances to date plus an estimate of contracts/change orders to complete the project.
  • This estimate can or have many revisions depending of the duration of the project (usually done every 1-2 months)
  • The last version of the Class A Revised is the actual final project cost
  • All unforeseen/defiencies changes are accounted financially
  • Project Modifier
  • Normally starts at 10% of the actual project cost and end up at 0% since the final actual project cost is know
5,6,7

 

Client (CT) - see Section 2: Roles and Responsibility.

 

Commissioning Agent (CXA) see Section 2: Roles and Responsibility.

 

Condition refers to a state reached by an asset at a point in its service life. It refers to a state of degradation, i.e. an irreversible process in or more characteristics of an asset with time, use or an external cause, such as lack of maintenance. It is expressed as a rating. A rating is a numeric value assigned to an asset based on its condition. The rating can be expressed using a facility condition index (FCI using VFA).

 

Condition Assessment refers to a systematic approach of identifying, assessing, prioritizing, and maintaining the specific maintenance, repair, renewal, and replacement requirements to provide valid documentation, reporting mechanisms, and budgetary information.

 

Contractor – The Contractor enters into a contract with the University to carry out a defined scope of work identified within the contract documents and undertakes responsibility for the coordination of the work including all of its sub-contractors. 

Critical Path refers to the series of activities that determines the duration of the project.

Current Replacement Value (CRV) is defined as the total amount of expenditure in current dollars required to replace the institution's facilities to its optimal condition. It should include the full replacement cost for all buildings, grounds, utility systems, and infrastructures.

 

Deferred Maintenance is the total amount of expenditures that would be required to perform maintenance projects that are not included in the capital renewal assessment and which were deferred as a result of unavailable resources or opportunity for scheduling.

 

Designated Substance Inventory – Identifies types and location of designated substances. Managed by the EHSO (Environment, Health and Safety Officer) of the University.

 

Engineer, Quality Assurance (EQA) see Section 2: Roles and Responsibility.

 

Facilities, in this context, refer to the space fitted-up, occupied and used by the occupants to carry out their function. All services emanating from the occupancy of the facilities are referred to facilities services. They include a wide range of services ranging from space layout and design to the environmental comfort of occupants.

 

Facility Condition Index (FCI) refers to a ratio of the cost of remedying existing deficiencies / requirements divided by the current replacement value (CRV).

 

Final Project Cost Report – Final costs once all activities are completed encumbered and paid.

 

General Conditions – See Bid document.

 

Master Drawing – Data bank of all up-to-date plans at the University (Archidata).

 

Mission and Objectives – Guiding elements for Physical Resources Service.

 

Monthly Executive Report – Monthly highlights of the project.

 

Operational is an on-going (or recurring) expenditure associated with operating and maintaining an asset. 

 

Operations and Maintenance Group (OM) see Section 2: Roles and Responsibility.

 

Payment Certificate – Confirmation of the payable amount of a contract (generally issued by the Architect).

 

Policy 113 on Maintenance, Renovations, Structural Modifications, Upgrading and Construction – Guiding rules that all must adhere to.

 

Procedure 19-2 on Selection Procedure for Consultants and Contractors) - Guiding rules that all must adhere to.

 

Project Types:

    New Construction Projects Space
    Optimization Projects
    Facilities Renewal Projects
    Energy Conservation Projects

 

Project Brief is a document that sets out the objectives of the project, the scope, the delivery elements, the time and cost factors, and any other factors. If need be, the Project Brief should state any special conditions to be respected by the Project Manager.

 

Project Accounting Group (PA) see Section 2: Roles and Responsibility.

 

Project Closeout Documentation Checklist – Enumerates all deliverables gathered by the Project Manager which needs final approval by Project Leader prior to completing all stages of a project.

 

Project Delivery Evaluation – Evaluation of a project on scope, schedule, cost, client satisfaction and major components. Statistical data used from these evaluations.

 

Project Estimate – Associates a cost per element of a project.

 

Project Identification Document – Basic information to understand the scope and major players allowing a project number to be issued.

 

Project Leader (PL) see Section 2: Roles and Responsibility.

 

Project Manager (PM) see Section 2: Roles and Responsibility.

 

PRS Standard Document – Enumerates technical standards which need to be considered in the design development.

 

Risk Management is a systematic way of identifying and analyzing potential risks and developing economic solutions to manage the risks. The sooner risks can be identified and solutions sought, the easier is their management and the less detrimental their impact.

 

Schedule “C” – Document that includes all the University supplementary conditions to the Canadian Standard Form of Contract for Architectural Services Document 6.

 

Standard Construction Documents (CCDC-2) – Standard form issued by the Canadian Construction Document Committee to be used by the construction industry for stipulated price contract (Lump Sum).

 

Standing Offers for Project Management, Consultants and Contractors – Following a request for proposal from the University and proposal received from invited firms, there are pre-negotiated agreements in which the fees and the services are pre-established in relation to the complexity of the projects.

 

UO Services providers – Protection, CCS, Audio-visual are services within the University that performs activities to the project.

 

User Group Representative - Users are those that will occupy and use the facility. More than one user necessitates the need to identify a User Representative, sometimes supported by a Committee, particularly during the planning and development phases.

 

Value Management provides value-added, cost-effective asset solutions to service needs through a structured, systematic and analytical process. The solutions need to provide all the necessary functions, and the required levels of quality and performance at the lowest total cost.

 

Work Order – The official contract between the University and the vendor (contractor or consultant) when under $250,000. Generally accompanied by the Short Form Bid Document.

Appendix B

This Procurement Procedure can be used by the Project Leader and/or the Project Manager at any stage of the project depending on when the consultants are hired.

Tasks – Professional Consultants

  Task Description                                   
CT
SP
PL
PM
EQA
CXA
PA
R/F
A.1 Review requirements of the Project Brief for specific instructions with respect to the procurement strategy  
empty black dot
2 black dot
black dot
empty black dot
     
A.2 Select procurement method in accordance with Procedure 19.2 and standing offers    
empty black dot
black dot
     
R
A.3 Select contract documents (see Contract Documents) for architects, engineers, project managers or other consultants    
2 black dot
black dot
     
F
A.4

Prepare Request for Proposal (RFP) to include as applicable:

    Statement of Work
    Definition of services required such as:

    (a) Functional Programming,

    (a) Schematic Design

    (b) Design Development

    (c) Construction Documents

    (d) Construction Procurement Method

    (e) Construction Contract Administration

University’s architectural standards and / or design criteria.

    (a) University’s engineering standards or criteria
    (b) CAD standards and record documents requirements
    (c) Commissioning requirements, as applicable, etc.

   
empty black dot
black dot
2 black dot
     
A.5 Invite consultants to a briefing to describe project, site, specific requirements and standards to be met, project budget, project milestones, evaluation method, and respond to any inquiries    
empty black dot
black dot
2 black dot
     
A.6 Respond to inquiries during the bid period and communicate both questions and responses to all bidders, and issue addenda, as required    
empty black dot
black dot
2 black dot
empty black dot
   
A.7 Receive proposals for services    
empty black dot
black dot
empty black dot
     
A.8 Evaluate proposals      
black dot
2 black dot
     
A.9 Select consultant or assemble the selection committee to appoint consultant(s)      
black dot
       
A.10 Issue Letter of Intent / Award      
black dot
   
2 black dot
 
A.11 Sign off or recommend for signature    
empty black dot
black dot
       
A.12 Award Contract    
empty black dot
black dot
   
2 black dot
 

Deliverables

  • Canadian Standard Form of Contract for Architectural Services